Purpose

The purpose of this phase is to conduct a complete business requirement gathering which can be used as basis for the SAP Business One system configuration.

Procedure

The following lists the tasks that have to be completed during the implementation phase

 

Task #

Description

Results

Est. duration

Team members

1

General project management

 

1.5 hours

 

1-1

Review project plan

- Review minutes from kick-off meeting
- Project plan is updated based on outcome of kick-off meeting

1 hour

SAP Business One project manager, client project manager

1-2

Schedule business requirements gathering workshops

- Business requirements gathering workshops are scheduled

0.5 hours

SAP Business One project manager, client project manager

2

Business requirements gathering

 

19 hours

 

2-1

Conduct business requirements gathering workshops

- Business needs defined in detail in the areas of:
* sales,
* purchasing,
* inventory management,
* production and MRP,
* financials and accounting,
* service management
* banking
* reporting
* Business Partner and Item Master Data
* chart-of-accounts

- Requirements defined for:
* authorizations and data ownership
* data migration
* interfaces and integration points
* system performance

15 hours
(5 workshops at 3 hours each)

SAP Business One consultant, client functional leads, client IT administrator

2-2

Create Business Blueprint

- All relevant data (requirements, solutions, limitations, and gaps) are documented in Business Blueprint document

4 hours

SAP Business One consultant

3

Review blueprint

 

5 hours

 

3-1

Review and discuss Business Blueprint

- Feasibility of business and technical requirements is determined
- Limitations and gaps are established and solutions are agreed upon

4 hours

SAP Business One consultants, SAP Business One project manager, client project manager

3-2

Review project plan

- Project plan is up-to-date based on Business Blueprint review

1 hour

SAP Business One project manager, client project manager

4

Review Project Phase

- Obtain signed project phase sign-off

1 hour

SAP Business One project manager, client project manager, SAP Business One consultants